News

Construction begins on building frame of children's hospital

Construction begins on building frame of children's hospital

The building frame of the new National Children's Hospital is now under construction as controversy continues over the projected cost of the project.

Excavation works at the St James' site in Dublin have been ongoing for the past year, but building of the frame, which can be seen above ground level, along with mechanical and electrical work has started.

The hospital could cost €2bn, more than €1bn more than what was approved by the government in 2017, due to an underestimation of how much money was needed to finish it.

However, the Chair of the National Paediatric Hospital Development Board, Fred Barry, has defended the decision to go ahead with the main contractor.

Advertisement

"Notwithstanding the difficulties in reaching an agreement with BAM, the view of the development board was that it was better to proceed with BAM rather than stop the project and re-tender the main construction works," he said.

"We could have re-tendered the project but it would have added years of delay and between tendering costs, inflation, increased owners costs and mobilisation costs, the likelihood was that re-tendering would ultimately result in higher project costs rather than lower."

Advertisement